Milestone Title, Deadline (Project month) and Status
MS1 Kick-Off Meeting (Month 1, March 2020) - Done
MS9 Website (Month 3, May 2020) - Done
MS3 Workshop Knowledge Transfer held (Month 7, September 2020) - Done
MS4 Workshop Kick-Off Consolidation held (Month 7, September 2020) - Done
MS5 Workshop Consolidation of LRI held (Month 13, March 2021)
MS6 Start of actual testing in the test-environment (Month 14, April 2021)
MS10 Event preparation workshop held (Month 15, May 2021)
MS7 Completion of testing (Month 20, October 2021)
MS8 Deployment of the national side of the LRI connection in the national production environment (Month 20, October 2021)
MS11 Dissemination Event held (Month 20, October 2021)
MS2 Project End (Month 20, October 2021)